 The earned value technique is a commonly used method of performance
measurement. It integrates project scope, cost, and schedule measures to help
the project management team assess project performance. If a project’s Schedule
Performance Index
SPI=EV/PV value less than 1.0,
it means that
 
.


A
the project is ahead of its planned schedule
B
less work was completed than was planned
C
the cost overrun for work completed
D
the cost underrun of performance to date
使用微信搜索喵呜刷题,轻松应对考试!

答案:

B

解析:

挣值分析技术是一种评估项目绩效的方法,它结合了项目的范围、成本和进度来衡量。其中的进度绩效指数(SPI)是已完成的挣得值与计划价值的比值。当SPI值小于1时,表示实际完成的进度比计划的少,即进度滞后。因此,选项B“进度滞后”是正确的答案。