Project schedule management is made up of six management processes including: activity definition, activity sequencing, ( ) , and schedule control by order.

A
activity duration estimating, schedule developing, activity resource estimating
B
activity resource estimating, activity duration estimating, schedule development
C
schedule developing, activity resource estimating, activity duration estimating
D
activity resource estimating, schedule developing, activity duration estimating
使用微信搜索喵呜刷题,轻松应对考试!

答案:

B

解析:

:项目时间管理过程包括活动定义、活动排序、活动的资源估算、活动历时估算、制定进度计划及进度控制等六个步骤。这些步骤具有先后顺序,其中活动的资源估算、活动历时估算和制定进度计划是其中的关键步骤。因此,正确答案是B选项。