()assesses the priority of identified risks using their probability of occurring, the corresponding impact on project objectives if the risks do occur, as well as other factors such as the time frame and risk tolerance of the project constraints of cost, schedule, scope, and quality.

A
Quantitative Risk Analysis
B
Qualitative Risk Analysis
C
Enterprise Environmental Factors
D
Risk Management Plan
使用微信搜索喵呜刷题,轻松应对考试!

答案:

B

解析:

定性风险分析(Qualitative Risk Analysis)是对已识别风险进行优先级评估的过程,它考虑风险发生的概率、风险对项目目标的影响,以及项目的范围、成本、进度和质量的约束和风险承受能力等其他因素。因此,根据题目的描述,正确答案是B,即定性风险分析。