Schedule development can require the review and revision
of duration estimates and resource estimates to create an approved(74)that can serve as a baseline
to track progress.
刷题刷出新高度,偷偷领先!偷偷领先!偷偷领先! 关注我们,悄悄成为最优秀的自己!
Schedule development can require the review and revision
of duration estimates and resource estimates to create an approved(74)that can serve as a baseline
to track progress.
题干中提到需要创建一个被核准的项目计划,该计划可以作为基线以跟踪进度。因此,正确答案是D,即项目计划。