When required the perform Integrated Change Control Process includes ()Which is a formally chartered group responsible for reviewing ting approving deferring or rejecting changes to the project and for ing and communicating such decisions

A
BBC
B
CCB
C
BCB
D
CBC
使用微信搜索喵呜刷题,轻松应对考试!

答案:

B

解析:

题干中提到“When required the perform Integrated Change Control Process”,即当需要进行综合变更控制过程时。接着描述了“Which is a formally chartered group responsible for reviewing, approving, deferring or rejecting changes to the project and for coordinating and communicating such decisions”,这是一个正式授权的小组,负责审查、批准、推迟或拒绝项目的变更,并协调和传播这些决定。这与选项B中的“CCB”相符,因此答案是B。