单选题

You are a project manager for a small project. Your project was budgeted for ¥500,000 over a six-week period. As of today, you've spent ¥260,000 of your budget to complete work that you originally expected to cost ¥280,000.  According to your schedule, you should have spent ¥300,000 by this point.  Based on these circumstances, your project could be best described as (74) .

A
ahead of schedule 
B
 behind schedule 
C
on schedule 
D
having not enough information provided 
使用微信搜索喵呜刷题,轻松应对考试!

答案:

B

解析:

根据题目描述,原计划预算为50万元,工期为六周。到目前为止,已经花费了26万元完成了一部分工作,但这一部分工作的预算原本是28万元。按照原计划,此时应该花费了30万元。因此,实际进度比计划落后了,答案为B,即“behind schedule(落后于进度)”。